Re: CJV4 - SAP Message No. CN619 - Control Key Not Available For Costs

$
0
0

Does the network profile have all the same control keys?  Check Activities under OPS4.

 

And Control Key on that Activity has a check next to Cost?

 

New projects are working fine?  Since it looks like it is a database inconsistency try changing the Control Key on that Activity to something else, Save, Cost, Change control key back, Save, Cost.

 

Or delete the activity and recreate with a different activity number.  I have seen strange behavior when deleting activities then recreating the same activity, it was like the activity was never deleted.

 

Worst case, delete the activity, then create a new network header on that project and use it for the new activity.

 

One off problems are a bear to trouble shoot.