Rajneesh,
I was going through the settings of OKTZ, where currently CCS 'Z1' is assigned to co.code 1000 for all plants (++++) belonging to 1000.
2 new cost components are needed in a newly created plant PL05.
My question- Can I create new CCS say 'Z2' with all components of Z1 + add new 2 components, and assign it to new plant PL05? This way, I can use current set of cost elements also + not affecting existing CCS.
I understand that cost estimate of PL05 plant can't be transferred to another plant or vice versa if CCS is different.
Beyond this, does it impact it anywhere for the current cost estimates or comparability?
Thanks for your inputs.
Nirav