Re: Need to force default planning plant on task list creation without letting it copying from the equipment

$
0
0

Hello Raneetha,

I do not think that is possible through customising.


-One way you can have a different value from the Equipment master is to:

  • First change the value of Planning plant in the Equipment master and Save.
  • Create and Save the Equipment-Tasklist (with this changed value of Planning Plant)
  • Then change the Planning plant value back to Original value in the Equipment master if it is required.

 

-Secondly, see whether the solution given by Ziv  here using GuiXT works for you.

 

-And yet another way is to go for Transaction variant thorough SHD0  .

 

 

Regards

KJogeswaraRao